Abstract

Tunnelling underneath the water body is the most challenging part of the underground project and requires specific study, design, monitoring, and highly skilled professionals that can complete the task with the help of modern and innovative engineering. This paper tried to cover construction challenges faced during the tunnelling underneath the Mithi river at Mumbai Underground Metro Line -3 twin tube, 5.50 m finished diameter (Colaba- Bandra- Seepz) including 152 m NATM tunnel and 4 nos. of cross-passages, which made project more precious and challenging. Apart from tunnelling underneath the river, tunnel alignment was curved also and TBM mining becomes more challenging. In this case study, will discuss the challenges from the geological investigation to the construction of TBM tunnelling, NATM tunnel and cross passage (CP) underneath the Mithi river. As the overburden thickness from the river bed to the tunnel crown portion was about 5 m with weathered basaltic breccia rock; challenges were complete the geological investigation, water seepage, tunnel segment design, tunnel alignment deflection, the opening of cross passage and chances of deflection in the tunnel during CP excavation through NATM methods. This paper would be beneficial for taking precautionary measures during the tunnelling underneath the water body for the future tunnel projects.

References

  1. Pandey, V. K. (2019)., Use of underground space for f., Research Journal of Engineering, 8(2), 23-28.
  2. Sethna, S. F. (1999)., Geology of Mumbai and surrounding area and its position in the Decan Volcanic Stratigraphy, India., Journal Geological Society of India, 53, 359-365.
  3. Sheth, H.C., Pande, K., Bhutani, R. (2001)., 40Ar–39Ar ages of Bombay trachytes: evidence for a palaeocene phase of Deccan volcanism., Geophys. Res. Lett., 28, 3513– 3516.
  4. Sukheswala, R.N. (1956)., Notes on the field occurrence and petrography of the rocks of the Bombay Island, Bombay., Trans. Min., Geol. Metall. Inst. India 50, 101– 126.
  5. Iyer Kavitha (2019)., Tunnelling under the Mithi: How Mumbai Metro is meeting the challenge., The Indian Express.
  6. Ramamirtham Anuradha (2022)., Mumbai metro line 03 alignment and study area., https://housing.com/news/mumbai-metro-line-3
  7. Iyer Kavitha (2019)., Google earth image of the studied area., https://indianexpress.com/ article/ explained /tunnelling-under-the-mithi-how-mumbai-metro-is-meeting-the-challenge-5727871/
  8. Geological Interpretation report (2019)., Mumbai Metro line -03, package 05, Mumbai, India.,
  9. Detailed tunnel design (2019)., Mumbai Metro line -03, package 05, Mumbai, India.,
  10. Rastogi V.K. (2008)., Instrumentation and monitoring of underground structures and metro railway tunnels., World Tunnel Congress 2008 - Underground Facilities for Better Environment and Safety – India.pp794-808.
  11. Project Instrumentation daily report (2021)., Mumbai Metro line -03, package 05, Mumbai, India.,
  12. BS 6164-(2019)., Health and safety in tunnelling in the construction industry − Code of practice., British Standards Institution